top of page

How to show progress on milestone only summary tasks

A summary task containing only milestones as sub-tasks will only show 0% or 100% complete. This can be frustrating as it doesn’t reflect the progress made.


Summary lines can't show progress when only contain milestones
Milestone progress now being reflected into the summary

It would be better to be able to report the progress as a % of the milestones under the summary which have been completed. Even better would be showing this progress on the Gantt chart.


Fixing the issue with MS project not showing milestone progress at the summary level
A summary line showing the progress on milestones

We need to use several Custom Fields; see below. It is possible to do the % complete aspect with fewer fields, as shown at the end.

  • Number1 – Count up the milestones which make up the summary

  • Number2 – Count up how many milestones have been completed

  • Number3 – Calculate the % complete for relevant summary tasks.

  • Text1 – Display the % complete shown in Number3 OR the standard % complete if the summary task contains any tasks

  • Flag1 – Identify if the summary task contains any tasks, in which case we have to use the standard % complete. It also allows us to manipulate the Gantt chart view

  • Finish1 – Calculate the “complete through” value for the summary tasks made up of milestones.

Right mouse menu to access custom fields
Right mouse menu to access custom fields

To add the custom field calculations to your plan right mouse click on the column headers and choose Custom Fields




Select the field you want to operate on, rename it and enter the required formula.










Field

Rename

Formula

Summary

Number1

Number of MS

IIf([Milestone],1,0)

​Rollup as Sum

Number2

​Completed MS

IIf([Milestone] And [% Complete]=100,1,0)

Rollup as Sum

​Number3

MS % Complete

IIf([Summary]=Yes And [Flag1]=No,([Number2]/[Number1])*100,[% Complete])

Use Formula

Text1

% Done

IIf([Summary]=Yes And [Flag1]=No,[Number3],[% Complete]) & "%"

Use Formula

Flag1

Inc Tasks?

IIf([Summary]=No And [Milestone]=No,"yes","no")

Rollup as OR

Finish1

MS Complete Through

IIf([Summary]=Yes And [Flag1]=No,ProjDateAdd([Start],([Duration]*[Number3]/100)),"NA")

Use Formula


Now you can add the new % done (Number3) column to your Gantt chart or reports. Note that as this is a completed field, you will not be able to change it. You may want to keep the standard % Complete field available to update tasks.

To display the progress bar on the Gantt chart

  • Double click on a blank space to bring up the bar Styles dialogue.

MS Project Bar Styles dialogue box
Bar Styles Dialogue showing the two additional styles

  • After the existing summary bar style, insert two spaces and name the two new styles as shown.

  • Apply the formatting you want to see for each style. In this example, we have different colours to show that one summary is the standard MSP % complete and the other is our calculation.

An excellent blog by Jerome Odeh inspired this blog. I have done things a little differently; this is the joy of MS Project – there are generally at least two ways to do something.

If you don’t need to display on the Gantt chart you could reduce the number of fields used by:

Field

Formula

Summary

Number1

IIf([Milestone],1,-1000000)

Rollup as Sum

Number2

IIf([Milestone]=Yes And [% Complete]=100,1,0)

Rollup as Sum

​Text1

IIf([Summary] And [Number1]>0,([Number2]/[Number1])*100,[% Complete]) & "%"

use formula


16 views0 comments
bottom of page